Burndown chart includes Descoped Tasks
The burndown chart seems to include work remaining hours for sprint tasks that have already been descoped. Example: 10 hours remaining in a sprint, burndown chart shows 15 because 5 have been descoped. Is there a way to configure the system so that descoped tasks hours are not included in the burndown chart. We are using TFS template Scrum for Team System v3.
Official
Response
-
Urban Turtle does not take the 'Descoped' state into consideration as it only pertains to the Scrum for Team System v3 process template.
We recommend that you move the remaining tasks to another iteration or area. You could also set the remaining effort to 0 on descoped tasks or you could remove them altogether by using the "Deleted" state.
-
Urban Turtle does not take the 'Descoped' state into consideration as it only pertains to the Scrum for Team System v3 process template.
We recommend that you move the remaining tasks to another iteration or area. You could also set the remaining effort to 0 on descoped tasks or you could remove them altogether by using the "Deleted" state. -
-
-