During sprint planning, whenever we start adding tasks under one product backlog item, we always add the same type of tasks -
1. [doc] write documentation
2. [review] review documentation with customer
3. [dba] change schema
4. [dev] update model
5. [dev] write api method
6. [dev] code review of api method
7. [dev] update mvc site
8. [dev] code review of mvc site
9. [qa/dev] integration tests
etc...
It would be great if urban turtle allowed me to define a 'template' with titles for each of the tasks above. Then I could with one click create all of the tasks above and update the details as needed.
Create a 'template' for creating multiple tasks under one backlog item with one click
-
Thank you for your feedback. Your suggestion has been added to our backlog.
-
-
-
-
This is still on our backlog but it has yet to be planned.
-
-
Hi Loius
This would be a very useful feature. It would make using Urban Turtle much more efficient.
Regards
John -
-
In sprint planning we often add a lot of the same tasks. Is there a way to duplicate tasks from one PBI to another? We often have to go into Excel to do this. It would be nice to do this in Urban Turtle.
This reply was created from a merged topic originally titled
Bulk Copy Task Items from one PBI to another. -
-